Davidson Residence Hall
page 1   |   page 2

August 29, 2004
The new residence hall was opened
to students.


August 13
The main entrance and stairway
were landscaped.


August 12
The hallways were painted and
furniture installed in the rooms.


August 5
The front of the residence hall took
shape.

July 27
Painting outside was nearly complete.


July 23
A shaft on the main floor was prepared for the elevator.


July 22
The foot bridge from the back
parking lot was completed.


July 9
Parking lot was complete while a second floor walkway was built.


June 26
Decorative rock was added to the base of the exterior walls and posts at the main entrance.


June 25

Drywall work was done inside.

 

June 25
Backside retaining wall and walkway edge the new parking area were created.

.
June 21
Cement sets up on the sidewalk from the rear parking area.

June 21
Forms prepared for cement staircase to the main entrance.

June 18
A walkway behind the hall was ready for concrete to be poured.


June 17
Staircase to the main entrance was
roughed-in.


June 17
Insulation inside was nearly complete

June 2, 2004
Windows and roof shingles were installed and building wrap had the residence hall "in the pink."

 

Click to view more Residence Hall construction photos.