May 17
The mansard roof sheeting was in
place. A central (flat roof) area was
still to come.


May 25
The gabled roof above the main lobby
was in place.


May 25
An electrician works near the
stairwell in the main lobby area.
 

May 17
View from the gym entrance ramp.


May 14
The parking area south of the new Hall
was enlarged


May 7
Looking up the hill behind the Academic Center

May 7
Roof framing takes shape.

April 30
Inside the lobby looking southeast.


April 29
Second story was complete and rafters were added.

April 21
Front porch area took shape.


April 13
From the Hall's back side. Ready for concrete to be pumped to create the second story flooring.


April 12
Putting on the first story ceiling.

April 6
Adding more walls and halls.

March 29
Raising the first story walls.

March 16
Installing the radiant heat tubing

which was embedded in

concrete. Metal framing was used.

March 11
Pouring the foundation and slab


March 5
Footings, leveling and preparing to pour the foundation.


February 22
Ground leveling began.
February 11
Clearing away brush and trees.

Work began on t February 10, 2004he original site.